Council House redevelopment

Posted: 29/02/2012

Council House - artist's impression of how it will look by November 2012

The Council House, our city centre headquarters, closed in December 2010 so that the building can be completely redeveloped. We intend to create an energy-efficient, fully accessible building with a fantastic customer service centre – one that will save us money in the long term. Main contractors BAM Construction and project managers Mace aim to complete the work by November 2012.

Progress of the redevelopment work

View the latest photographs of the building work at the bottom of this page. You can also watch some short films on our YouTube page which capture the redevelopment work in action:

Why we're redeveloping the Council House

1. We couldn't continue using the building as it was.

The Council House was in desperate need of refurbishment. There was a £14 million maintenance backlog on the building, all the old windows and cast iron radiators needed replacing, for instance. If we'd continued to occupy the building we would have had to have done that maintenance work.

We could have spent £14 million to patch the building up – but it still would not have been fit for purpose. Instead we intend to refurbish and extend the Council House, which will mean…

2. We set an example of how to redevelop an historic and iconic city centre building – keeping what's best about the external façade of the building but totally modernising and updating the interior.

3. We invest in the city centre – regenerating the building and creating jobs at a time when unemployment in the city is set to rise.

4. We open up the building to our customers and the people of Derby – in several ways:

  • We create a new customer service facility – a bigger, more open, more accessible space where customers will be able to get information and advice, and make payments, applications and appointments. It will be a ‘one-stop shop’ where members of the public can meet with other organisations too.
  • We put democracy literally at the centre of the Council House – with a redesigned, fully accessible Council Chamber, visible throughout the building.
  • We make the whole building compliant with the Disability Discrimination Act (DDA).

5. We use cutting edge initiatives to reduce the Council's carbon emissions – the redeveloped building will be designed to secure an ‘excellent’ rating under BREEAM (BRE Environmental Assessment Method) and an ‘A’ rated Energy Performance Certificate. The cutting edge initiatives will include a hydro-power station on the river Derwent and adiabatic cooling. Adiabatic cooling is where a fine mist is blown into the building at night; as the mist evaporates, it consumes heat energy and rehydrates the air.

6. We save taxpayers significant amounts of money in the long term – by knocking down the internal walls and creating open plan office spaces, we can accommodate more than three times the number of people in the building, using the same footprint. This means we can move employees out of other (inefficient) office buildings, reducing the amount we spend on rented office space and on utilities.

By building an extra floor at the top of the building, we can also rent out space to partner organisations – meaning we can generate income.

Why it makes financial sense

In the long term, there are significant financial benefits to be gained from refurbishing the Council House and moving all our city centre staff into the building. The overall cost of refurbishing and extending the Council House was originally estimated at £34million - already we expect the final cost to come in lower than this.

We are effectively taking out a mortgage to redevelop the Council House, secured against our other properties, which will be paid back over a 40 year period.

To offset the costs of repaying this mortgage, we will make the following savings:

  • Selling our St Mary's Gate and Roman House offices will generate around £4.6m – reducing the amount we need to borrow and saving us £305,000 a year.
  • Moving out of leased buildings such as Heritage Gate and St Peter's House will save approximately £600,000 a year.
  • Renting space in the refurbished Council House to partners will generate income of over £200,000 a year.
  • Renting out space at other Council buildings once we all move into the Council House will generate income of over £75,000 a year.
  • As a result of all the energy efficiency measures being built into the refurbished Council House, annual running costs are expected to be reduced by £150,000 a year.

These savings total £1.3m, meaning the cost of refurbishing the Council House is actually £0.92m a year.

If we just refurbished our current city centre buildings to a standard that would clear the maintenance backlogs, it would cost us £0.93m a year. This means we would spend more to stay in unsuitable office accommodation than it will cost us to refurbish and extend the Council House, giving our customers much better facilities and enabling more staff to work together under one roof.

Creating an open-plan space where all staff and services are based together is crucial to the delivery of our ‘one Derby, one council’ programme, which we anticipate will save us £20.8m over the next four years.

Media

  1. The tower crane is removed - 19th May 2012
  2. The tower crane is removed - 19th May 2012
  3. The tower crane is removed - 19th May 2012
  4. Glazed atrium, third floor
  5. Glazed atrium from above
  6. Customer service are and Council Chamber
  7. Walkway to the new Council Chamber (March 2012)
  8. Atria bringing natural light into office area (March 2012)
  9. Third floor office windows (March 2012)
  10. Circular roof light for the customer area (March 2012)
  11. New public viewing gallery above the Council Chamber (March 2012)
  12. Circular roof above the new council chamber and viewing gallery (March 2012)
  13. The Leader of the Council being interviewed inside the Council House (Feb 2012)
  14. The roof decking and central Council Chamber take shape (February 2012)
  15. The steel frame for the new third floor is erected (February 2012)
  16. The pre-cast concrete floors are installed between the steel frame (Feb 2012)
  17. A view of the tower crane sitting next to the Council Chamber (January 2012)
  18. A view of the central Council Chamber taken from the ground floor (January 2012)
  19. Existing slates being removed and replaced (January 2012)
  20. Initial stages of roof decking (January 2012)
  21. Laying floor decks to the Council Chamber area (January 2012)
  22. Aerial image showing the civic entrance (January 2012)
  23. Aerial image showing the eastern side of the building (January 2012)
  24. Aerial image showing southern side of the building and courtyard (January 2012)
  25. The steel frame of the new circular Council Chamber (December 2011)
  26. BAM Construction erects steelwork across the inner courtyard (December 2011)
  27. The steel frame of the new circular Council Chamber (December 2011)
  28. The steel frame of the Council Chamber takes shape (November 2011)
  29. Steelwork stretching across the inner courtyard (December 2011)
  30. The new steel frame starts to go up (November 2011)
  31. Rafters on the open plan second floor now exposed and preserved (November 2011)
  32. BAM Construction’s crane in place (November 2011)
  33. New open plan office space (September 2011)
  34. New open plan office space (September 2011)
  35. Demolition work by DSM Demolition (August 2011)
  36. Demolition work by DSM Demolition (August 2011)
  37. Second floor with internal walls demolished (August 2011)
  38. Demolition work by DSM Demolition (August 2011)
  39. DSM Demolition remove the 1960s ‘link bridge’ across the courtyard (May 2011)
  40. Inner courtyard – demolition work begins (May 2011)
  1. Some image

    The tower crane is removed from the new Council House - 19th May 2012

  2. Some image

    The tower crane is removed from the new Council House - 19th May 2012

  3. Some image

    The tower crane is removed from the new Council House - 19th May 2012

  4. Some image

    The glazed atrium and the new third floor - April 2012

  5. Some image

    The glazed atrium from above - April 2012

  6. Some image

    The new customer service area and Council Chamber - April 2012

  7. Some image

    The walkway to the new Council Chamber beneath the circular roof light.

  8. Some image

    One of the atria that will allow natural light into the office area (March 2012)

  9. Some image

    Windows looking into the new third floor offices (March 2012)

  10. Some image

    Circular roof light which will allow natural light in to the customer area (March 2012)

  11. Some image

    The new public viewing gallery above the Council Chamber (March 2012)

  12. Some image

    The circular roof above the new Council Chamber and viewing gallery (March 2012)

  13. Some image

    The Leader of the Council being interviewed inside the Council House (February 2012)

  14. Some image

    The roof decking and central Council Chamber take shape (February 2012)

  15. Some image

    The steel frame for the new third floor is erected (February 2012)

  16. Some image

    The pre-cast concrete floors are installed between the steel frame (February 2012)

  17. Some image

    A view of the tower crane sitting next to the Council Chamber (January 2012)

  18. Some image

    A view of the central Council Chamber taken from the ground floor (January 2012)

  19. Some image

    Existing slates being removed and replaced on top of new felt and battens (January 2012)

  20. Some image

    Initial stages of roof decking (January 2012)

  21. Some image

    Laying floor decks to the Council Chamber area (January 2012)

  22. Some image

    Aerial image showing the civic entrance and the steelwork across the central courtyard (January 2012). Courtesy of BAM Construction

  23. Some image

    Aerial image showing the eastern side of the building and the steelwork across the central courtyard (January 2012). Courtesy of BAM Construction

  24. Some image

    Aerial image showing the southern side of the building and central courtyard (January 2012). Courtesy of BAM Construction

  25. Some image

    The steel frame of the new circular Council Chamber (December 2011)

  26. Some image

    BAM Construction erects steelwork across the inner courtyard (December 2011)

  27. Some image

    The steel frame of the new circular Council Chamber (December 2011)

  28. Some image

    The steel frame of the Council Chamber takes shape (November 2011)

  29. Some image

    Steelwork stretching across the inner courtyard (December 2011)

  30. Some image

    The new steel frame starts to go up (November 2011)

  31. Some image

    Rafters on the open plan second floor now exposed and preserved (November 2011)

  32. Some image

    BAM Construction’s crane in place (November 2011)

  33. Some image

    New open plan office space (September 2011)

  34. Some image

    New open plan office space (September 2011)

  35. Some image

    Demolition work by DSM Demolition (August 2011)

  36. Some image

    Demolition work by DSM Demolition (August 2011)

  37. Some image

    Second floor with internal walls demolished (August 2011)

  38. Some image

    Demolition work by DSM Demolition (August 2011)

  39. Some image

    DSM Demolition remove the 1960s ‘link bridge’ across the courtyard (May 2011)

  40. Some image

    Inner courtyard – demolition work begins (May 2011)

On this page: