Latest news

OUR CITY OUR RIVER PROJECT UPDATES

 

 

Sowter Road / Duke Street

 

 The concrete wall around Christchurch Court is programmed to be installed by the end of January and brickwork cladding completed by mid-February, weather permitting. We still have some utility issues to resolve to complete the concrete works next to the bridge.

 

Once the flood wall has been completed we will be carrying out earthworks to the open ground adjacent the Silk Mill to improve the flood water flow path back to the river. These works are currently programmed to take three weeks from the end of February but are again weather dependant.

 

 

Chester Green Residents Parking Permits

Chester Green Residents are advised that a letter will be sent out next week informing them that their parking permits are free for another 12 months and instructing them how to renew their permits.
Any payments that have been made for renewals will be refunded on request.

 

 

 Work on lower City Road

From Monday 13th November 2017 for approx. 8 weeks, the following works will happen on lower City Road:

- the removal of the existing flood wall;
- closure of the gaps in the new wall;
- excavation and installation of the tree pits; ...
- reinstatement of the footpath;
- installation of the glass panels along the new wall;
- finish the brick work and copings.

During this time, there maybe an increase of noise and activity as these works progress.

Our hours of work are 7.30am to 5.00pm and work progression will be dependent on weather and engineering factors.

 

 

St Mary's Walk

On Monday 18th September 2017 St Mary’s Walk from Darley Lane down to Duke Street will close to pedestrians for approximately 12 weeks.

 

We are working in partnership with our contractor, GBV Ltd who are carrying out the construction works. They have a construction management plan in place and this covers issues such as noise mitigation, hours of work and traffic management requirements for construction vehicles.

 

If you would like to speak to someone about the work, please contact Peter Richardson, Site Agent at the City Road project compound on 07484 036691.

 

For more information about the  Our City Our River project:

Email ocor@derby.gov.uk

 

 ‌‌

 

Location of Sowter Road Closure

Map  to show areas where road closure takes place in sowter Road.

 

                                    

Diversion Routes for Duke Street Closure

Duke Street residents leaflet regarding road closure

 Map showing route of Sowter road diversion when closed

 

 

 

 

Darley Playing Fields


New sports facilities are to be constructed to replace those lost due to the OCOR flood defence works. A planning application has been submitted and we are awaiting approval.
The site area is within the Derwent Valley World Heritage site, Chester Green Conservation area and mainly within the Little Chester Roman Scheduled monument. The proposals and detailed levels of excavation have been developed in conjunction with Heritage England and Derby City Council Conservation officers. Depths of excavation have been provisionally agreed and the nature of archaeological monitoring established. This is subject to Scheduled Monument Consent approval.

  • Football pitches – the layout of the 12 pitches has been re-organised to facilitate the new flood defences.
  • Tennis courts – 4 new courts are to be constructed adjacent to the football pitches. These will be surfaced in macadam, have 3m high perimeter fencing and access from the main path.
  • 3G artificial surfaced court – Consultation with local sports clubs has shown demand for this type of facility for football practice. The court will be adjacent to the new car park on the ‘dry’ side of the new flood defences. It will have an artificial grass surface with sand and rubber crumb infill, a 4.5m and 3m high perimeter fence and floodlighting.
  • Informal sports area - To compliment the formal sports courts an informal sports area is to be sited adjacent to the 3G court. This will be permanently open to the public and provide a sports wall with goal and basketball hoop, a selection of outdoor gym equipment and seating.


Parkers Piece

  • Cricket Practice Nets – New nets are to be erected at Parker Piece.
  • Artificial cricket wicket – to be installed.
  • Drainage – to be installed across the field.

Slide show image

Contact me: Philip Margett, email: philip.margett@derby.gov.uk

To find out more about the Our City Our River flood defence project:

On this page: